PPT Slide
- Project approval by Participants Q4 1999 ?
- Project approval by Joint Authority Q1 2000 ?
- Award major equipment orders Q2 2000 ?
- Award fabrication contracts mid 2000
- Award HuC contract mid 2000
- Complete detailed design Q2 2001
- Drilling/initial installations Q1 2002
- Commence Offshore HuC Q1 2003